For nearly a year, Provo drivers have become accustomed to tacking on at least five extra minutes of travel time.
That’s because University Avenue — the city’s major north-south roadway that’s historically provided a quick, direct route to Interstate 15 — has long been clogged with cones and construction traffic.
It all hinges on the Utah Department of Transportation’s extensive work to replace the University Avenue Bridge. The long-standing viaduct carries drivers over the current end of the Utah Transit Authority’s FrontRunner network and above the Union Pacific Railroad’s switching yard.
Traffic can still cross on half of the bridge, which remains open to drivers as construction crews work to replace the other half. That work started in fall 2025.
This fall, crews will switch to working on the second half of the bridge with the hope that they can finish the entire project by fall 2027.
University Avenue is such a critical route that UDOT intentionally opted for a longer construction timeline in order to keep some traffic flowing, said Andy Spencer, UDOT’s project manager for the Provo, Vineyard and Lindon areas.
“It was a very useful bridge — it lasted 60 years —but everything does age and wear, and it was the time to replace it,” he said. The new bridge is expected to last another 75 years, according to UDOT.
(Trent Nelson | The Salt Lake Tribune) Traffic makes its way through the University Avenue Bridge construction zone on Monday, Aug. 10, 2026.
(Trent Nelson | The Salt Lake Tribune) A sign at a business in the University Avenue Bridge construction zone.
(Trent Nelson | The Salt Lake Tribune) Traffic makes its way over the University Avenue Bridge construction zone.
In the meantime, UDOT suggests drivers consider taking State Street southbound as an alternate path to I-15. Lanes have been added to that route to accommodate more cars.
But State Street itself has been clogged by construction recently. There, city crews are expanding a multi-use sidewalk trail from the Provo City Cemetery up north to 300 South.
That means, for now, cones are kind of unavoidable — and patience is appreciated.
“We are very grateful to have a public that has adapted to our construction,” Spencer said. “... We’ve actually been thrilled with how wonderful the public’s been to work with, and how they’ve listened to our messages.”
(Trent Nelson | The Salt Lake Tribune) Traffic makes its way through the University Avenue Bridge construction zone.