(Leah Hogsten | Tribune file photo) A state audit says that the Utah Transit Authority gave millions in sweetheart deals to developers, and also points out problems with the agency's long-term finances.
Study: Bus Rapid Transit better bang for buck than light rail
Study » UTA is happy with rail projects, but BRT is part of its plan.
First Published Sep 24 2013 05:14 pm • Last Updated Feb 14 2014 11:34 pm

The Utah Transit Authority figures the many new rail lines it opened in the last three years attracted $7 billion to $10 billion worth of new development near stations as a side benefit to improving transportation. Since it spent $2.4 billion on those lines, it sounds like a good return on investment.

But a new study says governments get even more bang for their buck in revitalizing areas if they instead build "bus rapid transit" (BRT) systems. While far cheaper to construct, they attract just as much development.

Join the Discussion
Post a Comment

The UTA says there is no need for buyer’s remorse for its new TRAX, FrontRunner and streetcar projects — because they do more than revamp areas. But UTA adds that BRT is a focus of its future plans. It is sort of a TRAX on rubber wheels where buses have exclusive lanes, passengers buy tickets from vending machines before boarding on platforms, and buses have priority at intersections.

"We are seeing that mass transit can revitalize cities if governments act wisely — and the type of mass transit providing the best bang for the buck is bus rapid transit," said Walter Hook, chief executive officer of the New York-based Institute for Transportation and Development Policy.

His institute released a report Tuesday, "More Development for Your Transit Dollar," that looked at development along 21 mass transit corridors in 13 cities in North America (but none in Utah). It concluded that BRT generates 31 times more development than the best light rail projects for each dollar spent. TRAX is an example of light rail.

The study said that a new BRT line in Cleveland generated $5.8 billion in transit-oriented development around its stops, while Portland’s new blue line light rail generated $6.5 billion. They were the top performers studied among the two types of transit.

But because the Cleveland line cost significantly less to build, the study says Cleveland leveraged 31 times more per dollar spent in attracting new development.

UTA has one partial BRT line so far — the MAX bus on 3500 South in West Valley City and Magna. However, only about a one-mile stretch currently is a true BRT with exclusive lanes for buses.

UTA is planning to soon add a BRT line between Provo and Orem, and is studying another between Taylorsville and Murray.

UTA has many others penciled in on long-range regional transportation plans, including along such places as Redwood Road, the Mountain View Corridor, State Street in Salt Lake County, Washington Boulevard in Weber County, Foothill/Wasatch Drive, 1300 East, 700 East and the Bangerter Highway corridor.


story continues below
story continues below

"We are excited to advance the unique benefits provided by BRT, and the potential for transit-oriented development along those corridors in addition to the transit-oriented developments that we have along the rail system," said UTA spokesman Remi Barron.

He adds that "the primary purpose of building mass transit systems is to serve a transportation need, not facilitate development." Barron said the light-rail TRAX has higher capacity than BRT "and is designed to serve a different transportation function" and was determined to be the best mode for the corridors where they were used.

"UTA is seeing great development activity and success around our light-rail system," including the City Creek mall in downtown Salt Lake City, Daybreak developments on the red line in South Jordan and West Valley City’s Fairbourne Station on the green line. He adds the soon-to-open Sugar House streetcar has attracted more than $1 billion in new development near it.

"While we would assert that BRT and light rail transit equally facilitate transit-oriented development, the decision to build BRT or LRT involves many considerations, only one of which is the facilitation of transit-oriented development," Barron said.

Hook, with the institute, said, "In these cash-strapped times, how far an investment stretches sparse government dollars is as critical as finding the lowest possible price tag for the project. Bus rapid transit fits perfectly in this narrow window of opportunity."

The study notes that BRT was developed in Brazil and has been embraced by cities in South America, North America and Asia. The biggest BRT system is in Bogota, Colombia, which averages 2 million riders a day.



Copyright 2014 The Salt Lake Tribune. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

Top Reader Comments Read All Comments Post a Comment
Click here to read all comments   Click here to post a comment


About Reader Comments


Reader comments on sltrib.com are the opinions of the writer, not The Salt Lake Tribune. We will delete comments containing obscenities, personal attacks and inappropriate or offensive remarks. Flagrant or repeat violators will be banned. If you see an objectionable comment, please alert us by clicking the arrow on the upper right side of the comment and selecting "Flag comment as inappropriate". If you've recently registered with Disqus or aren't seeing your comments immediately, you may need to verify your email address. To do so, visit disqus.com/account.
See more about comments here.
Staying Connected
Videos
Jobs
Contests and Promotions
  • Search Obituaries
  • Place an Obituary

  • Search Cars
  • Search Homes
  • Search Jobs
  • Search Marketplace
  • Search Legal Notices

  • Other Services
  • Advertise With Us
  • Subscribe to the Newspaper
  • Access your e-Edition
  • Frequently Asked Questions
  • Contact a newsroom staff member
  • Access the Trib Archives
  • Privacy Policy
  • Missing your paper? Need to place your paper on vacation hold? For this and any other subscription related needs, click here or call 801.204.6100.