(Paul Fraughton | Tribune file photo) As summer approaches, the Utah Department of Transportation announces $800 million worth of highway and road construction projects that will mean orange cones will begin appearing soon.
Another big I-15 project coming next year
Road construction » The plan is to add express lanes, replace bridges, rework interchanges.
First Published Sep 13 2013 04:17 pm • Last Updated Sep 13 2013 11:10 pm

Eagle Gate is an unofficial gateway to downtown Salt Lake City. Next year, Salt Lake County may have a much different kind of unofficial gateway for motorists on Interstate 15: orange construction cones.

State highway officials told the Utah Transportation Commission on Friday that a new, big I-15 project will begin in Davis County next year. That comes on top of an even bigger reconstruction project recently announced for next year around Point of the Mountain.

Join the Discussion
Post a Comment

"We skipped most of Salt Lake County. But we will be on both ends of it," north and south, said Kris Peterson, director of the Utah Department of Transportation’s Region One.

The newly announced project — estimated to cost $120 million — will add express lanes from North Salt Lake to Farmington, replace seven old bridges there and rework two other major interchanges at 2600 South in Woods Cross and 500 South in Bountiful (including improving access through them for pedestrians and bicyclists).

Work is expected to start early next year, Peterson said, and take about two years to complete.

UDOT had long planned three separate projects in Davis County, he noted — one to extend the express lanes, one to replace deteriorating bridges and another to rework problematic interchanges.

"When we obtained funding to do the express lanes," Peterson said, "we decided to try to combine the projects into one to reduce disruption."

He added that UDOT is putting out a request for proposals now to contractors to do the design-then-build project and hopes to have a winner under contract by January.

UDOT has enough funding to expand northbound express lanes between where they end now in North Salt Lake and where they begin again in Farmington, Peterson said. "And we will build southbound lanes as far as we can afford to," depending on how the bids come back.

Bridges are expected to be replaced at the 2600 South and 500 South interchanges and at 1500 South (two each in each spot, one for each direction), plus a single bridge over I-15 at 400 North. Peterson noted several of the bridges are old, and concrete falling from beneath them has caused problems.


story continues below
story continues below

UDOT is allowing total closure of the freeway for up to five weekends during the project for bridge-replacement work. Officials anticipate that contractors likely will choose to build bridges to the side of the freeway, and move them into place over a weekend.

"We have some good alternative routes," including Legacy Parkway for those weekend closures, Peterson said.

Officials anticipate that all current lanes will remain open during peak hours, with nighttime lane restrictions at various periods throughout the two-year project.

The Davis County project is not as major as the other work at the Point of the Mountain. "That is a total reconstruction of the freeway there. In Davis County, we are just squeezing in new express lanes plus the other work," Peterson said.

The project at the Point of the Mountain — which has the official nickname of "The Point" — is a $247 million effort to rebuild seven miles of I-15 between Draper and Lehi during the next two years.

It will also widen I-15 to six lanes in each direction from 12300 South in Draper to the Timpanogos Highway (State Road 92) at Thanksgiving Point. Some areas in that stretch now have four lanes, and some have five.

UDOT has said that is the last major section of I-15 on the Wasatch Front that has not been reconstructed in recent years. It is about 50 years old, and at the end of its life span. Sections of pavement there often have buckled in recent years because of dirt and debris clogging temperature expansion joints.

The new projects come after UDOT last December completed a massive $1.7 billion project over three years to rebuild and expand most I-15 stretches in Utah County.



Copyright 2014 The Salt Lake Tribune. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

Top Reader Comments Read All Comments Post a Comment
Click here to read all comments   Click here to post a comment


About Reader Comments


Reader comments on sltrib.com are the opinions of the writer, not The Salt Lake Tribune. We will delete comments containing obscenities, personal attacks and inappropriate or offensive remarks. Flagrant or repeat violators will be banned. If you see an objectionable comment, please alert us by clicking the arrow on the upper right side of the comment and selecting "Flag comment as inappropriate". If you've recently registered with Disqus or aren't seeing your comments immediately, you may need to verify your email address. To do so, visit disqus.com/account.
See more about comments here.
Staying Connected
Videos
Jobs
Contests and Promotions
  • Search Obituaries
  • Place an Obituary

  • Search Cars
  • Search Homes
  • Search Jobs
  • Search Marketplace
  • Search Legal Notices

  • Other Services
  • Advertise With Us
  • Subscribe to the Newspaper
  • Access your e-Edition
  • Frequently Asked Questions
  • Contact a newsroom staff member
  • Access the Trib Archives
  • Privacy Policy
  • Missing your paper? Need to place your paper on vacation hold? For this and any other subscription related needs, click here or call 801.204.6100.