(Scott Sommerdorf | Tribune file photo) Former Rep. Aaron Tilton heads Blue Castle, the company developing plans for Utah's first nuclear power plant. Opponents have filed suit against the state engineer's approval earlier this year for water rights for the project.
Utah gives green light to nuclear power plant
Power » Project meets demands of Utah law, engineer says; critics say lawsuits are coming.
First Published Jan 20 2012 09:58 am • Last Updated Mar 28 2012 12:24 pm

Plans for Utah’s first nuclear power plant cleared a big hurdle Friday, when State Engineer Kent Jones OK’d the use of Green River water to cool the proposed reactors.

Proponents called the decision an important step, made after lengthy and painstaking review. But critics said lawsuits are almost certain in light of the desert river’s importance for farmers, recreationists, endangered fish and some of the other 25 million people who rely on the water downstream.

At a glance

Online: Blue Castle Project info

Read more about the Blue Castle Project at the U.S. Nuclear Regulatory Commission website.

> 1.usa.gov/c3J4Xs

Community views

Pro » Mike McCandless, economic development director for Emery County, applauded Friday’s water-rights decision as a critical step forward to improving life in nearby Green River City and the rest of his 1,100-population county.

“We know it’s just one more step in the process,” he said, “but we in the county are very excited about it.”

The county estimates the plant will mean as many as 2,000 well-paying jobs. It also would roughly double the county’s tax base, he said.

Con » Green River farmer Tim Vetere criticized the decision to let the power plant take the river water.

“This is going to make it harder for farmers to get the water they need out of the river,” said Vetere, whose farm raises melons, sweet corn, field corn, hay and more. “Also, I’m worried that if a nuclear power plant goes in, people won’t want to buy my melons.”

“Pretending there is enough water in the Green River for the power plant is a mistake,” says Bob Quist, the owner of Moki Mac River Expeditions, a company that leads rafting trips on the Green. “It’s bad for my business and bad for everyone that depends on this river.”

Join the Discussion
Post a Comment

"The state of Utah has decided to up the contention over the Colorado," said John Weisheit, whose Moab-based environmental group was among the 200 organizations and individuals to protest the water proposal.

"There’s going to be litigation between the states," he predicted, "because [Utah officials] are allocating water that isn’t there. Someone upstream or someone downstream is going to suffer."

In what is expected to be the state’s only regulatory decision on the power plant, Jones said he focused on the law related to the request by water districts in Kane and San Juan counties to lease 53,600 acre-feet of their unused water rights to the power plant developers. After more than two years of study, he said, he and his staff found that Blue Castle LLC’s request would not harm other water users, wasn’t speculative and that there was water available, even during drought.

"From what we were looking at," he said, "there is adequate water for this project."

Jones acknowledged he’d fielded many concerns over safety and oversight, as well as water allocations and financial feasibility of the project. But state law guided his conclusion, he said.

"We have listened to and very much appreciate the concerns raised by those in the local community and others," Jones said in a statement. "Those concerns helped us look carefully and critically at the proposal as we considered the appropriate action on these applications."

Blue Castle CEO Aaron Tilton said the decision had been long in coming but was "exactly what we expected." Without water, the project could not have gone forward, he added.

"It’s one step but a hugely important step for us," said Tilton, a former state legislator. "It puts some momentum in the project."


story continues below
story continues below

The plant would be built on about 1,700 acres of a new industrial park in Emery County, near the intersection of State Route 6 and Interstate-70. It would include two reactors that would produce up to 3,000 megawatts of electricity.

Building the reactors is expected to cost up to $18 billion. And, if construction gets under way as planned in 2016, the plant could be generating nuclear power by 2020.

Yet, Blue Castle faces significant challenges ahead, such as completing a two-step U.S. Nuclear Regulatory Commission licensing process that is expected to cost $100 million.

And using the water is contingent on that approval, noted John Mann, assistant State Engineer. "They can’t do anything," he said, "until they get the NRC approval."

NRC spokesman Scott Burnell pointed out that Blue Castle isn’t expected to begin the first phase of licensing until 2013.

In that stage, the NRC looks at the proposed site broadly, asking the question ‘Is this the right place for nuclear reactors?’ Usually taking about three years, the analysis would include a look at impacts on the river, reductions in water levels, local housing and emergency services strains and a detailed environmental impact statement, Burnell noted. A later phase looks at the specific plant.

To approve the first-stage license, the NRC spokesman explained, "we would have to conclude that any impacts for the hypothetical power plant could be accounted for or corrected or the benefits of what’s being proposed wouldn’t outweigh the environmental cost."

It is not clear yet what role the U.S. Fish and Wildlife Service might play, but the agency is sure to be part of the discussion, given its charge to protect the habitat of four species of endangered fish: the Colorado pikeminnow, humpback chub, bonytail and razorback sucker.

The State Engineers’ decision notes that river flows sometimes fall below the targets set under a multiagency plan to preserve and restore the endangered fish as required under federal law.

"Approval of this application has the potential to exacerbate the low-flow situation," the water-rights decision says.

USFWS fish biologist Kevin McAbee said his agency will work closely with the NRC and Blue Castle to ensure the fishes’ survival.

Next Page >


Copyright 2014 The Salt Lake Tribune. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

Top Reader Comments Read All Comments Post a Comment
Click here to read all comments   Click here to post a comment


About Reader Comments


Reader comments on sltrib.com are the opinions of the writer, not The Salt Lake Tribune. We will delete comments containing obscenities, personal attacks and inappropriate or offensive remarks. Flagrant or repeat violators will be banned. If you see an objectionable comment, please alert us by clicking the arrow on the upper right side of the comment and selecting "Flag comment as inappropriate". If you've recently registered with Disqus or aren't seeing your comments immediately, you may need to verify your email address. To do so, visit disqus.com/account.
See more about comments here.
Staying Connected
Videos
Jobs
Contests and Promotions
  • Search Obituaries
  • Place an Obituary

  • Search Cars
  • Search Homes
  • Search Jobs
  • Search Marketplace
  • Search Legal Notices

  • Other Services
  • Advertise With Us
  • Subscribe to the Newspaper
  • Login to the Electronic Edition
  • Frequently Asked Questions
  • Contact a newsroom staff member
  • Access the Trib Archives
  • Privacy Policy
  • Missing your paper? Need to place your paper on vacation hold? For this and any other subscription related needs, click here or call 801.204.6100.