From the start, Dreamliner jet program was rushed


< Previous Page


There were also deep fears, especially among veteran Boeing workers, that "we were giving up all of our trade secrets to the Japanese and that they would be our competition in 10 years," Al-Kahwati said.

As the project fell further behind schedule, pressure mounted. It became increasingly clear that delivery deadlines wouldn’t be met.

Join the Discussion
Post a Comment

Each success, no matter how small, was celebrated. The first delivery of a new part or the government certification of an engine would lead to a gathering in one of the engineering building atriums. Banners were hung and commemorative cards — like baseball cards — or coins were handed out.

Those working on the plane brought home a constant stream of trinkets: hats, Frisbees, 787 M&Ms, travel mugs, plane-shaped chocolates, laser pointers and lapel pins. Many of the items can now be found for sale on eBay.

"It kept you going because there was this underlying suspicion that we weren’t going to hit these targets that they were setting," said Matt Henson, who spent five and a half years as an engineer on the project.

The world got its first glimpse of the Dreamliner on July 8, 2007. The date was chosen not because of some production milestone but for public relations value. It was, after all, 7/8/7.

Tom Brokaw served as the master of ceremonies at an event that drew 15,000 people. The crowd was in awe.

It was "beyond experiencing a rock star on stage," said Dressler, a former Boeing designer. "This thing is so sexy, between the paint job and the lines and the fact that it’s here now and you can touch it."

But like so much of show business, the plane was just a prop. It lacked most flight controls. Parts of the fuselage were temporarily fastened together just for the event. Some savvy observers noted that bolt heads were sticking out from the aircraft’s composite skin.

Boeing CEO Jim McNerney told the crowd that the plane would fly within two months.


story continues below
story continues below

Instead, the company soon announced the first of what would be many delays. It would be more than two years before the plane’s first test flight.

To overcome production problems, Boeing replaced executives and bought several of the suppliers to gain greater control. Work continued at breakneck pace.

"We were competing against time. We were competing against the deadline of delivering the first airplane," said Roman Sherbak, who spent four years on the project.

Then on a cold, overcast morning in December 2009, it all came together.

A crowd gathered at Paine Field, the airport adjacent to Boeing’s factory. The Dreamliner climbed deftly into the sky for a three-hour test flight.

But there were still plenty of glitches, including an onboard fire during a November 2010 test flight. Smoke had entered the cabin from an electronics panel in the rear of the plane. The fleet was grounded for six weeks. This month’s safety problems appear unrelated.

Deliveries were pushed back yet again.

Passengers wouldn’t first step aboard the plane until Oct. 26, 2011, three and a half years after Boeing first promised.

That first, four-hour journey — from Tokyo to Hong Kong — was more of a party than a flight. Passengers posed for photos as they climbed stairs into the jet. Alcohol flowed freely. Boeing executives were on hand, showing off the plane’s new features. Everybody, it seemed, needed to use the bathroom if only to check out the bidet and giant window inside.

More airlines started to fly the plane. Each new route was met with celebration. Travelers shifted itineraries to catch a ride on the new plane.

Boeing had hoped by the end of 2013 to double production of the Dreamliner to 10 planes a month. There are 799 unfilled orders for the plane, which carries a $206.8 million list price, although airlines often negotiate deep discounts.

Next Page >


Copyright 2014 The Salt Lake Tribune. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

Top Reader Comments Read All Comments Post a Comment
Click here to read all comments   Click here to post a comment


About Reader Comments


Reader comments on sltrib.com are the opinions of the writer, not The Salt Lake Tribune. We will delete comments containing obscenities, personal attacks and inappropriate or offensive remarks. Flagrant or repeat violators will be banned. If you see an objectionable comment, please alert us by clicking the arrow on the upper right side of the comment and selecting "Flag comment as inappropriate". If you've recently registered with Disqus or aren't seeing your comments immediately, you may need to verify your email address. To do so, visit disqus.com/account.
See more about comments here.
Staying Connected
Videos
Jobs
Contests and Promotions
  • Search Obituaries
  • Place an Obituary

  • Search Cars
  • Search Homes
  • Search Jobs
  • Search Marketplace
  • Search Legal Notices

  • Other Services
  • Advertise With Us
  • Subscribe to the Newspaper
  • Login to the Electronic Edition
  • Frequently Asked Questions
  • Contact a newsroom staff member
  • Access the Trib Archives
  • Privacy Policy
  • Missing your paper? Need to place your paper on vacation hold? For this and any other subscription related needs, click here or call 801.204.6100.