Salt Lake City airport overhaul finally taking flight | The Salt Lake Tribune
Get news, sports and politics alerts

Click here to manage your alerts
(Francisco Kjolseth | The Salt Lake Tribune) Having secured airline support to help paying the $1.8 billion tab, the city is moving forward with plans for an overhaul. Construction is expected to begin next year, with occupancy in a new, single terminal happening in 2018.
Salt Lake City airport overhaul finally taking flight
Transportation » Design work to start this year on $1.8B project’s concourses, central terminal.
First Published Jan 17 2012 07:22 pm • Last Updated Apr 05 2012 11:36 pm

Salt Lake City is throttling up the jets on its long-delayed airport reconstruction plan, plotting a $1.8 billion makeover to break ground next year with freshly secured airline support.

Mayor Ralph Becker on Tuesday night announced that the city had reached accord with Delta and the other airlines over the last month — a crucial step because the carriers would pay hundreds of millions of dollars toward the project — and said design work should begin this summer.

Photos
At a glance

Plans for a new and renewed airport

» One terminal to replace three and improve efficiency.

» Two new concourses extending east and west from terminal.

» Three existing concourses accessed through the new east wing.

» 74 multipurpose gates to replace 86, 30 of which are equipped only for short-hop commuter flights.

Join the Discussion
Post a Comment

A new airport with striking views of the mountains and a window to the future as a major hub would "express our ascendancy" as a city, Becker said in his State of the City address.

"Visitors to the airport," he said, "should experience a wonderful gateway to Salt Lake City, to our state and to the Intermountain West."

"It has been years of stop and go," the mayor said before his speech, with previous hopes dashed by, among other snags, post-9/11 business uncertainty and Delta’s bankruptcy restructuring.

But the airline support now means a more efficient Delta hub would help drive the city’s economic development, he said. A new, single terminal to replace the existing three at Salt Lake City International Airport could be ready by 2018.

David Hamm, Delta’s managing director of corporate real estate, said the rapidly aging hub and the earthquake risk prompted the decision for a complete overhaul.

"The conclusion at the end of the day is that building new provides a better economic return," he said. "It’s a fiscally responsible plan. The economics make sense to move forward."

Passenger numbers neared 21 million last year, marking a slow but steady increase.

"While still boasting top honors in on-time departures and receiving accolades for excellence, our airport’s aging facilities, seismic risks and need to accommodate growth, demand capital improvements," Becker said in his speech. "We need a new airport."

story continues below
story continues below

The plan would require incremental approval from the Federal Aviation Administration as construction stages progress. Given airline support, airport Executive Director Maureen Riley said, "we have every indication that they are excited about Salt Lake’s proposal."

The overhaul also would need annual budget approval from the City Council. The city would not pay the bill, though. Airlines would cover about $300 million in bonds for the project, Riley said, while passenger fees and fee-backed bonds would pay the largest share of the rest. Those fees already are maxed out at $4.50 per passenger flight segment, so they would not change unless Congress approves an increase.

Members of the City Council were excited by Tuesday’s announcement.

"We all know that our airport is dated and tired," Councilwoman Jill Remington Love said after the mayor’s address. "It’s great that we have a commitment from Delta going forward."

The airport, which is debt-free, also has $250 million in reserve from previous passenger fees. Other funds would come through federal grants and rental-car fees.

The new airport actually would have fewer gates, but would use them more efficiently to allow growth in flight numbers. Today’s airport has 86 gates, airport spokeswoman Barbara Gann said, but 30 of them are outdoor boarding areas used only for smaller regional flights. The new layout would have 74 gates, and all would be equipped to handle any flight.

The new terminal would replace 50-year-old Terminal 1, 33-year-old Terminal 2 and 15-year-old International Terminal. A new parking structure would replace the 20-year-old rental-car and short-term garage.

Next Page >


Copyright 2012 The Salt Lake Tribune. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

Reader Comments
Reader comments on sltrib.com are the opinions of the writer, not The Salt Lake Tribune. We will delete comments containing obscenities, personal attacks and inappropriate or offensive remarks. Flagrant or repeat violators will be banned. If you see an objectionable comment, click the red "Flag" link below it.
See more about comments here.
What are those badges some users have next to their names?


Staying Connected
Jobs
Shopping
Contests and Promotions
Affiliates and Partners